MEMORANDUM
TO: Zilker Condominiums Residents
FROM: Zilker HOA
DATE: October 22, 2009
RE: Project Update and Upcoming Foundation Repairs
______________________________________________________________________________
At the HOA meeting on September 23, 2009, the following items were approved by homeowners:
Foundation Repairs
Retaining Wall Repair
Soffit repair and installation of Hardi-Plank & drip edge
Step repair
Stucco repair along driveway
Upgrade of courtyard landscaping
Decorative entry fence with signage
Privacy fence in front of dumpster
New mailbox
Completion of fence along back of property*
2 bike racks*
*The fence at the back of the property and the bike racks may be postponed, depending upon the funds remaining after all other items (as well as any unexpected repairs) are completed.
Please take note of the following:
● The Foundation project is scheduled to begin Monday morning, November 2nd at 8:00am. Centex Foundation expects the work to take 3-6 weeks to complete.
● The driveway along the north side of the building will be closed for the duration of the foundation repairs. All cars must be moved from the back parking lot by Sunday evening, November 1st. Any cars remaining on Monday morning will be towed to the front lot & towing fees are the responsibility of the car’s owner.
The other projects will begin after the foundation work is done.
Thanks for your cooperation!